Maple House Project Information Page

MAPLE HOUSE PROJECT INFORMATION PAGE
Updated: 07/03/2023

Maple House 149 Tottenham Court Road, London W1

Welcome to our project information page, its purpose is to give you a regular update of what we the contractors are progressing with in regards to the refurbishment of Maple House. Regular newsletters will also be produced on a monthly basis to let you know what is going on and how it may affect you during the project.

View the latest Two Week Look Ahead  >Noticeboard 23

To receive regular updates on planned works, or if you have any concerns or enquiries, please email: maplehouse@fourcommunications.com

Proposed Works Being Undertaken:

Occupying an Island site on the east of Tottenham Court Road, the newly refurbished Maple House will offer c. 47,000 sq ft across three floors with an extensive refurbishment throughout including a remodelled reception and an extensive new central garden square complete with outdoor terracing.

Take a look at some of the CGIs of the proposed works below:

Working hours:

The works on-site will take place between the following hours:

  • Monday to Friday 08:00 to 18:00
  • Saturday 08:00 to 13:00
  • Sunday and Bank holidays, No work without prior notification and agreement with City of London

Contact Details:

Faithdean Plc – Site Management Team

Project Manager:  John Ferguson 
Tel. 07885 307153
Email – j.ferguson@faithdean.co.uk

Site Manager: John Martin
Tel. 07825 504207
Email – j.martin@faithdean.co.uk

Noticeboard Archive:

Noticeboard 22
Noticeboard 19
Noticeboard 18
Noticeboard 16
Noticeboard 15
Noticeboard 14
Noticeboard 13
Noticeboard 12
Noticeboard 11
Noticeboard 10
Noticeboard 9
Noticeboard 8
Noticeboard 7
Noticeboard 6
Noticeboard 5
Noticeboard 4
Noticeboard 3
Noticeboard 2